IT 導入プロジェクトに取り組んでいる営業チームは、プロジェクト マネージャーに何度か連絡を取り、残業代の不払いについて苦情を言いました。プロジェクト マネージャーは、他のチーム メンバーが残業代を受け取っていることに気づきました。プロジェクト マネージャーは次に何をすべきでしょうか?
正解:B
In the context of project management, when a team member or a group of team members raise an issue, the first step for the project manager is to validate the concern. If the issue is valid, it should be documented in the issue log for further action. The issue log is a project management tool used to capture and maintain the details of each issue in the project. It is a document that plays a central role in reducing project risk and is a record of all issues that have been identified or reported in the project, along with their status and resolution. It's also a communication tool that engages the project team in problem-solving. References: Project Management Articles, Webinars, Project Management Institute