イテレーションベースのマーケティング プロジェクトでは、製品は 6 回目のイテレーションで発売される予定です。 3 回目のイテレーションのデモで、マーケティング チームは、製品の発売までに 5 回のイテレーションが必要であるが、まだ開始されていないと表明しました。プロジェクト チームは何をすべきでしたかこの問題を回避するには?
正解:A
In an iteration-based project, the project team should collaborate with the stakeholders frequently and continuously to ensure that the product meets their expectations and needs. The project team should also identify and resolve any impediments or issues that may affect the delivery of the product. By holding a touchpoint with the marketing team before the demo, the project team could have aligned their expectations, clarified the requirements and constraints, and addressed any potential risks or challenges. This would have helped to avoid the issue of the marketing team needing more iterations to launch the product and not starting their work yet. References: (Professional in Business Analysis Reference Materials source and documents)
* PMBOK Guide, 6th edition, Chapter 5, Section 5.1.2.1, page 152
* PMBOK Guide, 6th edition, Chapter 6, Section 6.2.2.1, page 191
* PMBOK Guide, 6th edition, Chapter 13, Section 13.2.2.1, page 507
* PMBOK Guide, 6th edition, Appendix X3, Section X3.2.2, page 718
* PMI PMP-Project Management Professional Practice Exam Q. 781 to 790