プロジェクトのチームリーダーが組織を離れたため、経営陣はエンジニア A をこのポジションに昇進させたいと考えています。プロジェクト マネージャーは、エンジニア A を選択するとプロジェクトに問題が増えると確信しており、エンジニア B の方がこの役割に適していると考えています。プロジェクトマネージャーはすべての議論を経営陣と話し合いましたが、彼らの決定は変わりません。 プロジェクトマネージャーは何をすべきでしょうか?
正解:A
The project manager should support the decision made by the management and assist engineer A in transitioning into the new role. This includes providing the necessary training and resources to ensure engineer A is successful. Additionally, it's important to keep engineer B motivated and engaged, as their contributions are still valuable to the project. This approach aligns with the PMP objectives of promoting collaboration, supporting team development, and maintaining a productive team environment. References: = This answer is verified by the principles outlined in the PMBOKGuide, which emphasizes the importance of team development and management's role in project success1. Furthermore, the Professional in Business Analysis materials support the idea of fostering team skills and maintaining team morale2.