複雑なプロジェクトの実行中、プロジェクト マネージャーはさまざまなチームからの多数の変更要求に遭遇します。これらの変更により、プロジェクトが目的を達成できなくなる可能性があります。
プロジェクト マネージャーは、これらの変更が効果的に管理されるようにするにはどうすればよいでしょうか?
正解:B
Effective management of change requests involves evaluating the effects they have on the project scope, timeline, and finances. By recording these changes in the risk register, the project manager can make informed decisions and ensure the project's overall success. This approach allows for a structured process to assess the impact of each change and to determine the appropriate response, whether it be acceptance, modification, or rejection of the request.
References: = The PMBOK Guide highlights the importance of integrating risk management processes with change management activities. It recommends using tools like the risk register to document and monitor changes, ensuring they are aligned with the project objectives and managed effectively12. Additionally, the guide from Project Management Academy outlines the steps for managing change requests, which include recording them in the risk register34.