In project management, when risk owners do not implement the agreed-upon risk responses, it is important for the project manager to address this issue promptly to reduce risk exposure. The best approach is to meet privately with the risk owners and collaborate with them to remove any impediments to the risk responses1. This approach ensures that the risk responses are implemented effectively and that the project continues to progress as planned. It also maintains a positive team dynamic by addressing the issue directly with the individuals involved, rather than escalating the issue unnecessarily. References: PMP Questions ID 2355 your risk report shows that project risk exposure ...