プロジェクト マネージャーはソフトウェア開発プロジェクトを主導しています。最近、チームメンバーは、ここ数回の定期的なスタンドアップミーティング中に、主要な利害関係者が頻繁に割り込み、説明を要求し、計画外の変更を提案したと不満を述べています。この問題はプロジェクト チームにストレスを与え、私の作業を遅らせます。
プロジェクトマネージャーは何をすべきでしょうか?
正解:D
According to the PMBOK Guide, 7th edition, one of the project management principles is to "engage stakeholders to understand their interests and needs". This means that the project manager should communicate with the stakeholder and clarify the scope, objectives, and expectations of the project. The project manager should also explain the impact of the stakeholder's interruptions and changes on the team's performance and morale, and negotiate a mutually acceptable way to handle the stakeholder's requests. The project manager should also update the stakeholder register and the stakeholder engagement plan to reflect the stakeholder's influence and engagement level, and monitor the stakeholder's satisfaction throughout the project. References: PMBOK Guide, 7th edition, page 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23,
24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48...