プロジェクト マネージャーは、品質向上に関する期限付きの社内プロジェクトに割り当てられます。プロジェクトの実行中、プロジェクト マネージャーは、特定のチーム メンバーが他のチーム メンバーによって孤立していることに気づきます。
プロジェクト マネージャーが取るべき 3 つのアクションはどれですか? (3つお選びください)
正解:A,C,E
The project manager should take actions to address the issue of team member isolation, as it can affect the team's performance, morale, and communication. The project manager should not ignore the issue or leave it to the team members to resolve it by themselves, as this may worsen the situation or create conflicts. The project manager should also not identify the isolated team member as a risk and document it in the risk register, as this may be seen as blaming or stigmatizing the individual. Instead, the project manager should do the following:
* Arrange and conduct team-building sessions to improve team effectiveness. Team-building activities can help to foster trust, collaboration, and cohesion among team members. They can also help to resolve interpersonal issues, clarify roles and expectations, and enhance team identity and culture.
Team-building sessions can be formal or informal, and can include exercises, games, workshops, or social events. The project manager should plan and facilitate the team-building sessions according to the team's needs, preferences, and goals.
* Get feedback from other team members to understand what led to this situation. The project manager should communicate with the other team members to understand their perspectives and opinions on why the specific team member is being isolated. The project manager should use active listening, open-ended questions, and empathy to elicit honest and constructive feedback. The project manager should also avoid making assumptions, judgments, or accusations, and instead focus on facts and feelings. The project manager should use the feedback to identify the root causes of the problem and possible solutions.
* Obtain feedback from the isolated team member to understand the situation. The project manager should also communicate with the isolated team member to understand their situation and needs. The project manager should show respect, support, and concern for the individual, and create a safe and confidential space for them to share their thoughts and feelings. The project manager should also ask the isolated team member what they need or want from the team and the project, and how they can be more involved and engaged. The project manager should use the feedback to address the individual's concerns and expectations, and to help them reconnect with the team. References: Project Management Professional (PMP)Certification | PMI, Team Building in Project Management | PMI, Team Building | Project Management Professional (PMP) - GreyCampus, How to Provide Effective Feedback to Project Team Members | PMI, The most important feedback in a project and how to receive them - Twproject: project management software,resource management, time tracking, planning, Gantt, kanban