ある企業は、プロジェクトの予測的実施から機敏な実施に移行しつつあります。要件に基づいて、プロジェクト チームは予算を見積もり、ベンダーとの固定価格契約を使用することを決定します。ただし、プロジェクトの実行中に要件が進化し、優先順位が常に変化し始めるため、プロジェクトと完了時の見積もり (EAC) が 40% 遅れます。
プロジェクトマネージャーは次に何をすべきでしょうか?
正解:C
The project manager should meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem, as this type of contract is more suitable for agile projects that have changing requirements and priorities. A T&M contract allows the buyer to pay the seller based on the actual hours of work and the cost of materials, rather than a fixed price. This can provide more flexibility and adaptability for the project, and reduce the risk of budget overrun. The other options are not as effective or appropriate as recommending a T&M contract. Sending a detailed status report may inform the stakeholders of the issue, but it does not propose a solution. Submitting a change request may increase the funding, but it does not address the root cause of the problem, which is the mismatch between the contract type and the project approach.
Waiting until the next gate review meeting may delay the resolution of the problem, and increase the likelihood of further deviation from the EAC. References:
* PMBOK Guide, 7th edition, page 163
* PMI-PBA Exam Content Outline, 2018, page 10
* PMP question 391