新しいオンライン ランディング プラットフォームを実装するプロジェクトが開始されました。最初のスプリントの後、プロジェクト スポンサーが変更を要求しました。プロジェクトマネージャーは次に何をすべきでしょうか?
正解:D
According to the PMBOK Guide, the project manager is responsible for managing changes and ensuring that they are aligned with the project objectives and scope. One of the tools and techniques for managing changes is change control tools, which include a change log, a change management system, and a configuration management system. When a change request is received, the project manager should use these tools to record, track, and approve or reject the change request. In addition, the project manager should also update the project documents and plans that are affected by the change request. One of the project documents that may need to be updated is the product backlog, which is a prioritized list of features and requirements that the project team delivers in sprints. The product backlog is a dynamic document that can change as the project progresses and new information is discovered. Therefore, the project manager should facilitate the update of the product backlog to reflect the change request and ensure that the project team and the project sponsor are on the same page regarding the project scope and deliverables. References: PMBOK Guide, 6th edition, pages 115-116,
123-124, 541-542.