プロジェクト マネージャーは、実行フェーズの終わりに近づいているプロジェクトを管理しています。上位の関係者は、プロジェクト マネージャーに、非常に重要な要件がプロジェクトの範囲に含まれていないこと、その要件がなければプロジェクトは何の価値も提供しないことを通知します。
プロジェクトマネージャーが最初にやるべきことは何ですか?」
正解:C
The first thing the project manager should do is to evaluate the impact that the inclusion of this new requirement will have on project performance. This is because the project manager needs to assess how the new requirement will affect the project scope, schedule, cost, quality, risk, and stakeholder satisfaction. The project manager should also consider the feasibility, desirability, and viability of the new requirement, and whether it aligns with the project objectives and business case. Based on the impact analysis, the project manager can then decide whether to accept or reject the change request, or to escalate it to the appropriate authority for approval. The project manager should also communicate the results of the impact analysis to the stakeholder and explain the rationale behind the decision. References:
* Change Management | What is Change Management | Prosci
* What Is Project Scope? Scope Management Steps, Tips & Tools
* Definition of Change Management - Prosci