プロジェクトの範囲は、半径 10 km 以内の道路標識の交換です。クライアントは、市議会の開発計画に合わせて半径を 1 km 延長しない場合、プロジェクト終了報告書に署名したくないと考えています。 プロジェクトマネージャーは何をすべきでしょうか?
正解:D
When a client requests a scope change, such as extending the project radius by 1 km, the project manager should first obtain formal acceptance for the work that has been completed within the original scope. Following this, the project manager should submit a change request to address the new requirement. This process is in line with the PMBOK Guide's Change Management Process, which includes identifying the change, analyzing its impact, documenting it, and presenting it to the Change Control Board (CCB) for approval1. References: * PMBOK Guide's Change Management Process For PMP Certification1. * Project Management Institute's official references for the PMP certification2. * Professional in Business Analysis Reference Materials provided by PMI2.