進行中の住宅プロジェクトのライフサイクル開始から1年が経過した頃、自治体から、プロジェクトのスケジュールと予算に大きな影響を与える新たな規制に関する通知を受けました。プロジェクトマネージャーは次に何をすべきでしょうか?
正解:B
A change request is a formal proposal to modify any document, deliverable, or baseline of a project. A change request should be submitted when a change is needed due to an external or internal factor, such as a new regulation, a stakeholder request, or an error correction. The Integrated change control process is the process of reviewing and approving all change requests, and managing the changes to the project management plan, project documents, and project baselines. The project manager should submit a change request through the Integrated change control process as the next step after receiving the announcement from the municipality, as this will ensure that the change is properly evaluated, approved, and communicated to the relevant stakeholders. Performing a qualitative risk analysis, updating the issue log, or estimating the associated costs are not the next steps that the project manager should take, as they do not address the need for a change request or the approval of the change. References: [PMBOK Guide 6th Edition], page 115; Project Management Professional (PMP) Exam Questions for 2022, question 23.