プロジェクトマネージャーは、要件が厳密に定義された政府機関向けのプロジェクトを、予測的なアプローチで主導しています。プロジェクトの途中で、スポンサーから重要な新機能の追加が要求されました。この機能は当初の計画にも、計画プロセスにも含まれていませんでした。プロジェクトマネージャーはどのように対応すべきでしょうか?
正解:D
According to the Project Management Body of Knowledge (PMBOK) guide, when a significant change is requested that was not part of the original plan, the project manager should first analyze the impact of this change on the project's scope, schedule, cost, and resources. This analysis should then be presented to the senior manager or project sponsor, who can make an informed decision about whether to proceed with the change.
This approach ensures that the implications of the change are fully understood before any action is taken, and it allows the project's stakeholders to make decisions based on the most accurate and up-to-date information.
This is a key aspect of effective change management in project management. References: PMBOK Guide,
6th Edition, Section 4.5: Perform Integrated Change Control.