アジャイル プロジェクトは 10 回中 6 回目の反復段階にあります。反復レビュー後、チームは関係者からフィードバックを受け取り、製品の変更につながる可能性があります。プロジェクト マネージャーが実行すべき 2 つのアクションは何ですか。(2 つ選択してください)
正解:A,B
In an agile project, the project manager should collaborate with the stakeholders and the product owner to manage changes in the product. Asking the stakeholders about the priority of this change will help the project manager understand the value and urgency of the change, and align the expectations of the stakeholders with the project vision. Asking the product owner to review the product backlog will help the project manager ensure that the change is properly prioritized and incorporated into the product backlog, which is the source of requirements for the agile project. Asking the team members to analyze the impact of this change, asking the sponsor to approve the change request, or asking the team members to include the change in the next iteration are not the best actions to take in an agile project, as they may introduce unnecessary delays, bureaucracy, or scope creep. References: = PMBOK Guide, 6th edition, page 18, section 1.2.3 (Agile Considerations); page
176, section 5.1.1.1 (Project Stakeholders); page 179, section 5.1.3.1 (Project Charter); page 181, section
5.2.1.1 (Product Owner); page 182, section 5.2.3.1 (Product Backlog)