これは、プロジェクト チーム内で混乱を引き起こしており、バックグラウンドでスコープが変更されているにもかかわらず、プロジェクト ミーティングでのみ言及されています。
プロジェクトマネージャーはこれにどう対処すべきでしょうか?
正解:A
The project manager should communicate directly with the director and inform them of the communications management plan, which defines how the project information will be exchanged among stakeholders, including the client. By doing so, the project manager can clarify the roles and responsibilities of the project team and the director, and ensure that the project scope is managed according to the agreed process. This will also help to avoid confusion, conflicts, and unauthorized changes in the project. References: (Professional in Business Analysis Reference Materials source and documents)
* PMBOK Guide, 6th edition, section 10.1.3.1, page 366
* PMP Exam Prep, 10th edition, Rita Mulcahy, page 357
* PMP Practice Questions #49 - iZenBridge1