プロジェクトの 3 回目の反復中に、既存のチーム メンバーのうち 2 名が入れ替わりました。プロジェクトが次の反復に入ると、チームの速度が低下し、パフォーマンスが低下し始めました。
プロジェクトマネージャーは何をすべきでしょうか?
正解:C
According to the Professional in Business Analysis Reference Materials, team building is a tool and technique used in the Develop Project Team process, which aims to improve the performance of the project team and enhance project outcomes. Team building activities can help the project manager to address the issues that arise from team member changes, such as loss of trust, communication gaps, and conflicts. Team building can also help the project manager to align the team members with the project goals and expectations, and to motivate them to achieve the key performance indicators (KPIs) that measure the team's progress and success. References:
* Professional in Business Analysis Reference Materials, page 176, section 9.3.2.3
* PMI PMP Quiz:35 Topic:1 Questions:171-175, question 3