新しいソリューションの導入のためにプロジェクト マネージャーが任命されます。ソリューションは、サード パーティ ベンダーによって環境に統合されます。このベンダーは、主要コンポーネントの提供が遅れることを発表しましたが、これはプロジェクト スケジュールに影響を及ぼします。
プロジェクトマネージャーは何をすべきでしょうか?
正解:B
The project manager should ensure that relevant stakeholders and expectations are identified and assess the component delay. This is because the project manager needs to communicate with the stakeholders about the impact of the delay on the project objectives, scope, schedule, cost, and quality, and seek their feedback and support. The project manager also needs to evaluate the component delay and its root cause, and determine the best course of action to address the issue. Asking for expedited delivery, performing a detailed analysis, or proposing a new design are possible actions that the project manager may take after ensuring stakeholder identification and assessment, depending on the outcome of the evaluation. However, they are not the best actions to take in this situation, as they may not address the stakeholder needs and expectations, or may introduce unnecessary changes or risks to the project. References: = PMBOK Guide, 6th edition, page 513, section 10.1.1.1 (Stakeholder Identification); page 518, section 10.1.3.1 (Stakeholder Register); page 520, section 10.2.1.1 (Stakeholder Analysis); page 524, section 10.2.3.1 (Stakeholder Engagement Assessment Matrix); page 526, section 10.3.1.1 (Communication Requirements Analysis)