ある銀行は、中小企業や起業家へのサービス提供から中規模・大規模企業へのサービス提供への移行プロジェクトを開始することを決定しました。国の経済は低迷しており、一部の利害関係者はこの変革の必要性について合意できません。プロジェクト マネージャーは何をすべきでしょうか。
正解:D
In the context of a project transition, especially one that involves a significant shift in business focus, effective communication is crucial. A communications management plan ensures that all stakeholders are informed about the project's progress, changes, and challenges. It helps to align the stakeholders, manage their expectations, and address their concerns, which is particularly important when there is disagreement about the need for transformation. The plan should include the types of information to be communicated, the methods of communication, the frequency of communication, and the parties responsible for the communication. References: Project Transition Planning: Process, Checklist, Tools - KnowledgeHut, What Is a Project Transition Checklist? (With Example) - Indeed