メンテナンス プロジェクトのプロジェクト マネージャーは、毎年更新される契約を結んでいます。このプロジェクトは6年前に始まりました。今年の契約更新後、監査人はこのバージョンの契約が昨年可決された新法に違反していると報告した。
この状況で何が起こったのでしょうか?
正解:A
According to the PMBOK Guide, the project team is responsible for conducting procurement activities, such as planning, conducting, controlling, and closing procurements. This includes reviewing and updating the contracts as needed to ensure compliance with the project requirements and the applicable laws and regulations. The project manager should also involve the legal department and other relevant stakeholders in the contract review process to avoid any potential issues or disputes. Therefore, if the contract violates a new law that was passed last year, it means that the project team has not performed an adequate review of the contract before renewing it, and has failed to identify and mitigate the risk of non-compliance. References:
* PMBOK Guide, Chapter 12, Section 12.1, Plan Procurement Management
* PMBOK Guide, Chapter 12, Section 12.2, Conduct Procurements
* PMBOK Guide, Chapter 12, Section 12.3, Control Procurements
* PMBOK Guide, Chapter 12, Section 12.4, Close Procurements
* PBA Guide, Chapter 5, Section 5.3.2, Contract Review and Approval