要件の引き出しプロセスでは、ビジネスアナリストとチームが要件の引き出しアクティビティの準備をする必要があります。要件の引き出しに備えるためにビジネスアナリストが必要とする3つの具体的な情報があります。
次のうち、ビジネスアナリストが要件の引き出しの準備をするときに使用する3つの入力の1つではないものはどれですか。
正解:B
Explanation
A change request is not one of the three inputs the business analyst will use as he prepares for requirements elicitation. A change request is a document that proposes a modification to the project scope, schedule, budget, or quality after the project has been initiated. A change request is usually submitted by a stakeholder who wants to add, remove, or change a requirement or a feature of the project. A change request is not an input for preparing for requirements elicitation, but rather an output of the requirements management process12.
The other options are the three inputs the business analyst will use as he prepares for requirements elicitation. They are3:
Solution scope: The solution scope defines the boundaries and features of the solution that will address the business need. It helps the business analyst to focus on the relevant requirements and to avoid scope creep.
Business need: The business need is the problem or opportunity that the project aims to solve or exploit.
It aligns with the strategic goals and vision of the organization. It helps the business analyst to understand the purpose and value of the project and to elicit the stakeholder needs and expectations.
Stakeholder list: The stakeholder list identifies and categorizes the people or groups who have an interest or influence in the project. It helps the business analyst to plan the appropriate elicitation techniques, communication methods, and stakeholder engagement strategies.
References:
Change Request - IIBA
Change Request - PMI
Prepare for Elicitation - IIBA