あなたは組織のビジネスアナリストであり、別のビジネスアナリストであるスティーブと一緒に新しいソリューションの要件を引き出しています。スコープクリープを防ぐために要件を追跡する必要があることをSteveに警告します。
スコープクリープとは何ですか?
正解:A
Explanation
Scope creep is the change or expansion in the project scope that occurs without proper assessment and approval. It can result in cost overruns, delays, and client satisfaction issues. Scope creep can happen due to unclear or changing requirements, lack of stakeholder involvement, poor communication, or inadequate change control. To prevent scope creep, business analysts should define the project scope clearly, manage stakeholder expectations, document and prioritize requirements, and follow a change management process.
References:
Scope Creep: Definition, Examples & How To Prevent It - Forbes
What is Scope Creep and 7 Ways to Avoid it [2023] * Asana
What is the meaning of Scope Creep in Project Management?