正解:A
Explanation
A RACI chart is a graphical representation of roles and responsibilities of different project team members. It is a matrix that shows the relationship between the project activities and the project roles. RACI stands for Responsible, Accountable, Consulted, and Informed. These are the four levels of involvement that a project team member can have in a project activity. A RACI chart can help to clarify the expectations, avoid confusion, and improve communication among the project team and stakeholders. References:
CBAP / CCBA Certified Business Analysis Study Guide, 2nd Edition, page 343 Business Analysis Professional Resources | IIBA, under Business Analysis Body of Knowledge (BABOK ) Guide What is a RACI Chart? | RACI Chart Definition & Example | ASQ