CEO は、企業が将来により大きな利益を得るために、複雑な金融商品の開発を許可しました。この予算は、すべてのリスクができるだけ早く特定されることを期待する世界的な投資家からの資金調達を通じて獲得されました。
プロジェクト マネージャーはリスクを特定するために何を使用する必要がありますか?
正解:C
Expert judgment is a technique that uses the knowledge and experience of experts to identify risks in a project. Experts can be internal or external to the project team, and they can provide insights on the sources, causes, and effects of potential risks. Expert judgment can also help to assess the probability and impact of risks, as well as the appropriate responses to them. According to the PMBOK Guide, expert judgment is one of the tools and techniques for the Identify Risks process, which is part of the Project Risk Management knowledge area. The other tools and techniques are data gathering, data analysis, interpersonal and team skills, and prompt lists. The other options are not tools and techniques for the Identify Risks process, although they may be used in other risk management processes or activities. An analysis of shared risks between parties is a way of identifying common risks that affect multiple stakeholders or projects. A SWOT analysis is a strategic planning tool that evaluates the strengths, weaknesses, opportunities, and threats of a project or organization. A risk value assessment is a method of prioritizing risks based on their expected value, which is the product of their probability and impact. References:
* PMBOK Guide, 6th edition, pages 397-398, 419-420
* Project Management Professional (PMP) Certification Handbook, page 9
* Risk Identification in Project Management, section "PMP Risk Identification Lifecycle"