高品質な製品で知られる大手国内企業が、あるプロジェクトを支援するため、小規模な下請け会社を選定しました。下請け会社のプロジェクトマネージャーは、プロジェクトが顧客の基準に沿って納品されることを確認するために、プロジェクトチームと会議を開いています。この基準を満たすために、プロジェクトマネージャーはどのような点を明確にし、文書化すべきでしょうか?
正解:D
In order to ensure that a project is delivered according to the customer's standards, the project manager should define and document the project's requirements. Requirements are the detailed inputs and outputs, processes, and other needs that a particular product, system, or service must fulfill to meet the customer's standards. They provide a clear picture of what the end product should be and how it should perform. By defining and documenting these requirements, the project manager can ensure that the project team has a clear understanding of what needs to be done to meet the customer's expectations. References: Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition. Project Management Institute, Inc. (URL: https://www.pmi.org/pmbok-guide-standards
/foundational/pmbok)1.