To ensure that project risks are reported accurately in the risk register, it is essential to review the risks throughout the project execution. This involves continuous monitoring and updating of the risk register to reflect new risks, changes in risk status, and the effectiveness of risk responses. Regular review allows the project manager to provide stakeholders with the most current information about project risks, which is crucial for informed decision-making and effective communication at the executive level123. : The approach aligns with best practices in risk management, which emphasize the importance of ongoing risk identification, analysis, and response planning as outlined in the PMBOKGuide and other PMI standards123.