緊急を要する建設プロジェクトにおいて、監督者と技術者の間で誤解が生じました。この誤解は深刻な対立に発展し、技術者はプロジェクトマネージャーに対し、監督者の指揮下ではこれ以上仕事を続けることができないと訴えました。監督者は、技術者のパフォーマンスの低さを対立の原因として挙げています。プロジェクトマネージャーはこの問題をどのように解決すべきでしょうか?
正解:C
According to the PMBOK Guide, conflict management is the process of identifying and addressing differences that, if left unresolved, could affect project performance1. The project manager should use appropriate conflict resolution techniques to facilitate constructive interactions among stakeholders and foster a collaborative project environment2. One of the conflict resolution techniques is collaborating, which involves incorporating multiple viewpoints and insights from different perspectives, and leads to consensus and commitment3. In the given scenario, the project manager should use a direct, collaborative approach with the technician and supervisor to understand the root cause of the conflict, address their concerns, and find a mutually acceptable solution that does not compromise the project objectives. This approach would also help to improve the relationship and trust between the technician and supervisor, and enhance their performance and motivation. References:
* 1: PMBOK Guide, 6th edition, p. 504
* 2: PMBOK Guide, 6th edition, p. 505
* 3: PMBOK Guide, 6th edition, p. 507