オペレーション マネージャーは、プロジェクトが会社にもたらす利益について継続的に懸念を表明しています。一部の懸念は正当なものですが、ほとんどの場合、これらの懸念がプロジェクト ミーティングの遅延を引き起こしています。プロジェクト マネージャーは、これをどのように処理すればよいでしょうか。
正解:B
The project manager should review the operations manager's concerns and ensure these concerns are addressed, as this is part of managing stakeholder engagement. Stakeholder engagement involves communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement. By reviewing and addressing the concerns, the project manager can increase the stakeholder satisfaction and support for the project, as well as avoid potential conflicts and delays. The other options are not the best ways to handle this situation, as they either ignore, escalate, or document the concerns without resolving them. References: (Professional in Business Analysis Reference Materials source and documents)
* PMBOK Guide, 6th edition, Chapter 13, Section 13.3
* PMP Exam Content Outline, June 2019, Domain II, Task 9
* PMP Sample Test Questions, Question 163