プロジェクト憲章の承認後、プロジェクト マネージャーは関係者とともに詳細なプロジェクト要件、制約、想定事項について検討する必要があります。ただし、関係者全員がすぐに短期間で会議に参加できるとは限りません。
プロジェクトマネージャーは、関係者から必要な情報を収集するために何をすべきでしょうか?
正解:A
According to the PMBOK Guide, the project manager should collect requirements from all stakeholders, using various techniques such as interviews, focus groups, surveys, etc. The project manager should also document the stakeholder requirements, expectations, and assumptions in the requirements traceability matrix.
If some stakeholders are not available for a meeting, the project manager should use other communication methods to reach out to them and gather their input. This will ensure that the project requirements are complete, accurate, and aligned with the stakeholder needs and expectations. References: PMBOK Guide, 6th edition, pages 140-141, 152-153.