正解:C
The burnup chart indicates that the "Completed" work is trailing behind the "Scope," suggesting that the team is not meeting the expectations set by the product owner. This discrepancy can be due to various factors such as underestimation of tasks, unforeseen challenges, or scope changes. It's important for the project lead to address this with the product owner and team to realign expectations, reassess the workload, and implement corrective actions to ensure that project goals are met within the sprint timeframe.
References:
A Guide to the Project Management Body of Knowledge (PMBOKGuide)
The PMI Guide to Business Analysis
Business Analysis for Practitioners: A Practice Guide12345.