あるプロジェクトで情報セキュリティサービスを提供するためにサプライヤーが雇用されました。サプライヤーは、支払いが期日通りに行われなかったため、このサービスの提供を中止することを決定しました。彼らのサービスは極めて重要であり、この決定はプロジェクトの成果に影響を与えるでしょう。
この問題に対処するためにプロジェクトマネージャーは何をすべきでしょうか?
正解:D
project objectives, scope, schedule, cost, quality, resources, or risks. The project manager should also seek their support and guidance on how to resolve the issue. In this case, the project manager should communicate with the project sponsor, the customer, the functional managers, and any other stakeholders who may be affected by the supplier's decision. The project manager should also explore alternative options for obtaining the information security services, such as negotiating with the supplier, finding another supplier, or performing the service internally. However, these options may have implications for the project budget, schedule, quality, and risk, and should be evaluated carefully before making a decision. References:
(Professional in Business Analysis Reference Materials source and documents)
* PMBOK Guide, 6th edition, Chapter 13, Section 13.3.2.4, page 513
* PMBOK Guide, 6th edition, Chapter 10, Section 10.2.2.4, page 385
* PMBOK Guide, 6th edition, Chapter 12, Section 12.2.2.4, page 471
* PMBOK Guide, 6th edition, Chapter 11, Section 11.5.2.4, page 443