計画セッションの後、新しいプロジェクトが開始されました。このプロジェクトは組織の幹部の直接監督下にあります。レビュー会議の後、プロジェクト マネージャーは、チーム メンバーの 1 人がプロジェクト全体のステータスを表示するためにダッシュボードを要求しているのを耳にしました。
プロジェクトマネージャーは何をすべきでしょうか?
正解:B
Explanation
= The project manager should tell the team member to route the request through the project manager, as this is the best way to ensure that the communication is consistent, accurate, and aligned with the project objectives.
The project manager is responsible for managing the communication with the stakeholders, including the executive, and for providing them with the appropriate level of information. The project manager should also verify the validity and feasibility of the request, and update the communications management plan accordingly. The other options are not the best actions to take in this situation, as they do not follow the established communication protocols or respect the project manager's authority. References: = A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 5: Project Communications, Section 5.2: Manage Communications, Page 137-138.