企業のチーム能力開発計画の一環として、プロジェクト マネージャーは、プロジェクト チームに必要なトレーニングのリストを管理者に提供するよう求められました。プロジェクトマネージャーは何をすべきでしょうか?
正解:B
Explanation
The project manager should review the team members' latest performance, identify gaps in competencies, and decide on the needed trainings, as this is one of the key processes in the Project Resource Management knowledge area. According to the PMBOK Guide, the project manager should assess the team members' skills, knowledge, and abilities, and compare them with the project requirements and expectations. The project manager should also identify the areas where the team members need improvement or development, and plan the appropriate trainings or interventions to enhance their competencies and performance. Reviewing the project pipeline, identifying gaps in competencies for execution, and deciding on the needed trainings (A) is not the best option, as it does not consider the individual needs and preferencesof the team members, and may not address the current issues or challenges they are facing. Reviewing the project schedule and the team members' performance, and deciding on soft skills and related trainings needed for the team is not sufficient, as it may not cover the technical or functional skills that the team members may also need to perform their tasks effectively. Reviewing the gaps found during project execution, preparing a list of recommended trainings, and discussing it during a team meeting (D) is not advisable, as it may not involve the team members in the decision-making process, and may not reflect their feedback or input. References: PMBOK Guide, 6th edition, pages 313-314, 333-334; PMP Examination Content Outline, pages 9-10, 13-14.