組織は、複雑なプロジェクトに対してハイブリッド配信アプローチを使用しています。イテレーションレビューでは、上級マネージャーが提示された機能の完全な再設計を求めています。これには、技術アーキテクチャの大幅な変更と追加のリリースが必要になる場合があります。
プロジェクトリーダーは最初に何をすべきでしょうか?
正解:C
Explanation
The project lead should first discuss with the product owner, who is responsible for defining and prioritizing the product requirements and ensuring that they deliver value to the customer and the organization. The project lead should understand the rationale behind the senior manager's request and the impact it would have on the product vision, scope, and schedule. The project lead should also collaborate with the product owner to assess the feasibility and desirability of the proposed redesign and determine the best way to handle it in the hybrid delivery approach. This approach is consistent with the principles of stakeholder engagement, communication management, and agile project management. References:
PMBOK Guide, 6th edition, pages 51-52, 513-514, 686-687.
PMP Exam Content Outline, June 2019, pages 6-7, 10-11, 16-17.