プロジェクト マネージャーは、既存の製品のメジャー アップグレードを処理している最中です。プロジェクト マネージャーは、プロジェクトの一部として当初約束されていたリソースが別の優先プロジェクトに移動されていることを知りました。
プロジェクトマネージャーは何をすべきでしょうか?
正解:D
Explanation
= This answer is based on the agile practice of backlog refinement, which is the process of reviewing, updating, and prioritizing the backlog items with the project team and other stakeholders. By reviewing the items remaining in the backlog with the project team, the project lead can ensure that the team has a clear and shared understanding of the project scope, requirements, and value. This will also help to identify and address any changes, dependencies, risks, or issues that may have occurred during the suspension of the project. This approach will enable the project team to resume the development activities with confidence and alignment. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
14: Enabling Change, Section 14.2: Leading the Team, page 334.
Agile Practice Guide, Chapter 3: Life Cycle Selection, Section 3.3: Implementing Agile: Creating an Agile Environment, page 32.