Explanation The project manager should spend a short amount of time defining the scope and building prototypes to refine the requirements for the new agile project. This way, the project manager can embrace the agile principle of delivering value early and often, and responding to changes in customer needs and expectations. The project manager can also use the prototypes to solicit feedback from the stakeholders and incorporate them into the next iteration of the product. The project manager should not create a scope baseline, estimate the work and story sizes, or develop a plan to complete more work in less time, as these are more suitable for predictive projects thathave fixed scope and requirements. References: PMBOK Guide, 6th edition, page 177, Top 20 PMP Sample Question and Answer For 2023 | StarAgile