プロジェクトの終了時に、プロジェクト マネージャーはプロジェクト チーム メンバーのパフォーマンス評価を提供するように求められました。プロジェクトマネージャーは主に何を参照する必要がありますか?
正解:B
Explanation
According to the PMBOK Guide, the project manager should evaluate the performance of the project team members based on the agreed-upon KPIs, which are measurable values that demonstrate how effectively the team is achieving the project objectives. The KPIs should be defined and communicated at the beginning of the project, and monitored and reported throughout the project lifecycle. The KPIs can include metrics such as quality, schedule, cost, scope, customer satisfaction, and team engagement. The project manager should use the KPIs as the main reference to provide a fair and objective performance rating of the team members, and to recognize and reward their contributions. References: PMBOK Guide, 7th edition, pages 27, 28, 29, 30, 31,
32, 33, 34, 35, 36, 37, 38, 39, 40, and 41. Quizlet.