ある企業は、自社のプロジェクトのために常に地元企業から非常に専門的なサービスを獲得してきました。規制プロジェクトの計画段階で、プロジェクト マネージャーは、予期せぬ重大な出来事により地元のベンダーが営業できなくなることを知らされました。他の国の企業から同じサービスを利用するオプションもあります。
この状況でプロジェクトマネージャーは何をすべきでしょうか?
正解:B
Explanation
According to the PMBOK Guide, 6th edition, procurement management is the process of purchasing or acquiring the products, services, or results needed from outside the project team to perform the work.
Procurement management can be done in a virtual environment, where the project manager and the vendors communicate and collaborate using online tools and platforms. This can help the project manager to overcome thechallenges posed by the unexpected major event that prevents the local vendors from operating. Planning to execute the procurement tasks in a virtual environment can also help the project manager to maintain the project schedule, scope, and quality, as well as to manage the risks and stakeholder expectations. References:
PMBOK Guide, 6th edition, Chapter 12: Project Procurement Management1; PMI, 2023, PMP Exam Content Outline2, Domain II: Process, Task 8: Plan and manage procurement activities.
1: PMBOK Guide, 6th edition 2: [PMP Exam Content Outline]