複数の下請け業者がいる複雑なプロジェクトで、1 つの下請け業者がスケジュールに遅延が発生する可能性があると報告しました。これは他の下請け業者に影響を与え、納期どおりに納品する能力に影響を与える可能性があります。
プロジェクトマネージャーは最初に何をすべきでしょうか?
正解:D
Explanation
When a project faces a potential delay in the schedule, the project manager should not report, change, or escalate the issue without first assessing the impact and the root cause of the delay1. The project manager should analyze the schedule to determine how the delay affects the critical path, the float, and the dependencies of the project activities2. The project manager should also update the risk register, which is a document that records the identified risks, their probability, impact, response strategies, and status3. Updating the risk register can help the project manager identify and prioritize the risks associated with the delay, and plan appropriate responses to mitigate or avoid them4. References: 1: PMBOK Guide, 6th edition, p. 112 2:
PMBOK Guide, 6th edition, p. 202 3: PMBOK Guide, 6th edition, p. 414 4: PMBOK Guide, 6th edition, p.
417