Linda は組織のビジネス アナリストであり、新しいビジネス アナリストである Joe と協力して要件の優先順位付けを行っています。Joe は、要件を優先順位付けする必要がある理由を理解していません。すべての要件は必須であるため、分析では同等の重みを持つ必要があります。要件を優先順位付けする必要がある理由について、Linda は Joe に何と説明すればよいでしょうか。
正解:B,D
A: Prioritization ranks the requirements according to the cost and schedule: This is an incorrect answer, as it confuses prioritization with estimation. Estimation is the process of determining the effort, time, and resources needed to implement the requirements. Prioritization is the process of determining the relative importance and urgency of the requirements.
B: Prioritization ranks the requirements on a weighted scale of key performance indicators, such as cost, schedule, risk, and experience: This is a correct answer, as it describes one possible method of prioritizing requirements based on multiple criteria that reflect the value and feasibility of the requirements. Key performance indicators (KPIs) are measurable factors that indicate the progress and success of the project or the solution.
C: Prioritization ensures that the most important stakeholders are considered first: This is an incorrect answer, as it implies that some stakeholders are more important than others. Prioritization does not rank the stakeholders, but the requirements. All stakeholders should be considered and involved in the business analysis process, as they have different needs, expectations, and perspectives that affect the solution.
D: Prioritization of requirements focuses on the most critical requirements first: This is a correct answer, as it states the main purpose and benefit of prioritization. Prioritization helps to ensure that the most valuable and essential requirements are delivered first, and that the scope, schedule, and budget of the project are aligned with the business objectives and stakeholder expectations.