プロジェクト マネージャー (PM) は、ビジネス アナリスト (BA) とともにプロジェクトのタイムラインを計画しており、要件割り当てのタスクに遭遇します。PM は、要件割り当てタスクを開始する前に依存関係を知りたいと考え、BA にアドバイスを求めます。次のどれが、BA が要件割り当ての先行として強調する依存関係ですか。
正解:A
Requirements architecture is the structure and organization of requirements that ensures they are complete, consistent, and aligned with the business need1. Requirements architecture is a dependency that the BA will highlight as a predecessor for requirement allocation, which is the process of assigning requirements to solution components, releases, or iterations2. Requirements architecture must be approved before requirement allocation can begin, to ensure that the requirements are stable, clear, and traceable. The other options are not direct dependencies for requirement allocation, although they may influence the process. References:
1: BABOK® Guide v3, Chapter 5: Requirements Analysis and Design Definition, Section 5.2: Structure and Organize Requirements
2: BABOK® Guide v3, Chapter 5: Requirements Analysis and Design Definition, Section 5.5: Allocate Requirements
3: Business Analysis Expert Certification, CCBA® | IIBA®