建築工事の実施中、サプライヤーは新しい安全規制の導入により、納期遅延や資材費の増加を招く可能性があります。チームは、一部の作業の遅延を短縮することで、このコストを吸収する選択肢を特定しました。
この状況を確実に管理するために、チームは何をすべきでしょうか?
正解:A
According to the PMBOK Guide, specifically within the Project Risk Management knowledge area, the project is currently in the Execution Phase, and a specific risk (delivery delay/cost increase due to regulations) has transitioned from a possibility to an active issue or a highly imminent event.
Why Choice A is correct: The team has already identified the risk and identified an option (reducing lag to absorb costs). This means the processes of Identify Risks, Qualitative Analysis, and Plan Risk Responses have effectively been completed for this specific scenario. The next logical step in the risk lifecycle, according to the Monitor Risks and Implement Risk Responses processes, is to actually execute the decided-upon strategy.
" Implementing the response " ensures that the identified workaround (reducing lag) is put into action to mitigate the impact of the supplier ' s delay and cost increase.
Analysis of other options:
B (Plan Project Risk Management): This is the high-level process of defining how to conduct risk management activities. It happens during the planning phase, not during the execution when a specific risk needs handling.
C and D (Perform Quantitative/Qualitative Risk Analysis): These are used to prioritize and analyze the impact of risks. Since the team has already " identified an option to absorb the cost, " the analysis of the situation ' s impact is already understood well enough to have formulated a solution.
By moving to Implement Risk Responses, the Project Manager ensures that the project remains on schedule and within the adjusted parameters, directly addressing the threat to the project ' s baselines.