正解:C
Based on the PMBOK Guide (specifically within the Project Schedule Management knowledge area, formerly Project Time Management), the Develop Schedule process is where the project scope statement and resource calendars are integrated to create the project schedule model.
* Role of the Project Scope Statement: This document contains the details of the project deliverables and the work required to create them. It provides the " Scope Baseline " context (including assumptions and constraints) that must be considered when determining the schedule ' s logic and boundaries.
* Role of Resource Calendars: These identify the working days and shifts on which each specific resource (human or material) is available. You cannot finalize a schedule without knowing when the resources are available to perform the work.
* Process Interaction: While Resource Calendars are also an input to Estimate Activity Durations, the Develop Schedule process is the specific point where the Project Scope Statement, Resource Calendars, Activity List, Network Diagrams, and Duration Estimates are all combined using techniques like Critical Path Method (CPM) to produce the final Schedule Baseline.
* Comparison with Other Options:
* Sequence Activities (A): Focuses on the logical relationship between tasks (dependencies), primarily using the Activity List and Attributes.
* Estimate Activity Resources (B): This process actually produces resource requirements; it uses the Activity List but does not take the Scope Statement as a direct primary input in the same way Develop Schedule does.
* Control Schedule (D): This is a monitoring and controlling process that uses the completed schedule as a baseline to measure performance; it doesn ' t use the Scope Statement as a primary input for day-to-day control.