プロジェクトマネージャーはアジャイル/アダプティブ環境で作業しています。プロジェクトマネージャーは、この環境でプロジェクト統合管理を適用するためのさまざまなアプローチを検討しています。
プロジェクトマネージャーは、これがプロジェクトで機能することをどのように確認できますか?
正解:B
According to the PMBOK Guide, specifically the section on Trends and Emerging Practices in Project Integration Management, the role of the project manager changes significantly in agile and adaptive environments.
* Collaborative Integration: In an agile environment, expectations for project integration management shift from the project manager being the sole " integrator " to the entire team sharing the responsibility.
The project manager focuses on building a collaborative environment where the team has the autonomy to make decisions about the detailed product planning and execution.
* Responding to Change: Agile environments are characterized by high uncertainty and rapid change.
Therefore, the " integration " happens through frequent iterations and constant communication. A team that is empowered to make decisions can respond to changes much faster than a team operating under a traditional, centralized command-and-control structure.
* Role of the PM: The project manager ' s focus moves toward fostering a team that can self-organize and ensuring that the team has the necessary tools and environment to integrate their own work effectively.
This aligns with the " Servant Leadership " model often cited in the Agile Practice Guide.
Analysis of Other Options:
* A. Take control of all decisions and product planning: This describes a traditional, predictive (Waterfall) approach. In an agile environment, taking total control inhibits the team ' s ability to be flexible and respond to the evolving product backlog.
* C. Promote a team with a narrow specialization within a hierarchical environment: Agile thrives on cross-functional teams (T-shaped professionals) rather than narrow specializations. Hierarchical environments often create silos that slow down the integration process.
* D. Delegate project decisions to the product owner and sponsor: While the Product Owner makes decisions regarding the " what " (product features/prioritization), project integration involves the " how
" and the coordination of the work. Total delegation of all decisions removes the necessary leadership and facilitation required from the project manager and the team.