正解:D
According to the PMBOK Guide, specifically within the Acquire Resources process, Pre-assignment is a tool and technique used when project team members are identified in advance.
* Definition: Pre-assignment occurs when physical or team resources for a project are determined before the project starts or before the human resource management plan is completed.
* Common Scenarios for Pre-assignment:
* Certain people are promised as part of a competitive proposal or bid.
* The project is dependent upon the specific expertise of a particular person (as mentioned in the question: " crucial to the task " ).
* Staff assignments are defined within the Project Charter itself.
* Impact on the Project Manager: When resources are pre-assigned, the project manager does not have to negotiate for them or acquire them through a standard hiring process; however, they must ensure these specific individuals are available when the scheduled activities occur.
Analysis of Other Options:
* A. Acquisition: This refers to the process of gaining resources from outside sources (e.g., hiring new employees or subcontracting) when the performing organization lacks the required staff.
* B. Negotiation: This involves the project manager working with functional managers or other project teams within the same organization to " borrow " or assign staff to their project. This is used when the resources are not pre-assigned.
* C. Virtual team: This is a technique where people with little or no time spent meeting face-to-face work together. While it helps in utilizing staff who are not in the same geographic location, it is a method of organizing the team rather than a method of selecting a specific crucial member in advance.