プロジェクトの現在のコスト パフォーマンス インデックス (CPI) は 1.25 です。現在までに、プロジェクト作業の実行に 10,000 米ドルが費やされました。現在までに完了した作業の稼得価値はいくらですか?
正解:D
According to the PMBOK Guide, specifically within the Control Costs process, the Cost Performance Index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as the ratio of earned value to actual cost.
* The Formula: The formula for CPI is:
$$CPI = \frac{EV}{AC}$$
Where:
* EV (Earned Value): The value of the work actually performed expressed in terms of the approved budget assigned to that work.
* AC (Actual Cost): The total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component.
* The Calculation:
Given the values from the question:
* $CPI = 1.25$
* $AC = \$10,000$
We rearrange the formula to solve for EV:
$$EV = CPI \times AC$$
$$EV = 1.25 \times 10,000$$
$$EV = 12,500$$
* Interpretation: A CPI of 1.25 means that for every dollar spent on the project, the project has earned
$1.25 worth of work. Since the CPI is greater than 1.0, the project is currently under budget (performing efficiently).
Comparison with Other Options:
* A. US$8,000: This would be the result if the CPI were 0.8 ($0.8 \times 10,000$). A CPI less than 1.0 indicates the project is over budget.
* B. US$9,500: This would be the result if the CPI were 0.95.
* C. US$10,000: This would be the result if the CPI were 1.0 ($EV = AC$), indicating the project is exactly on budget.
* D. US$12,500: This is the correct mathematical result of the provided CPI and Actual Cost.