あるビジネスアナリストが、海外に勤務する専門家(SME)にインスタントメッセージで複数の会議出席依頼を送信しましたが、返信がありませんでした。今後、他の関係者が複数の拠点に分散している場合、このような事態が発生する可能性を減らすために、ビジネスアナリストはどのような対策を講じるべきでしょうか?
正解:A
In the Plan Communications Management process of the PMBOK Guide, the primary goal is to ensure that the right information reaches the right person at the right time through the most effective channel.
Why Choice A is correct:
Stakeholder Requirements: Communication is not " one size fits all. " Factors such as culture, organizational hierarchy, and personal work styles influence how stakeholders interact. In some cultures, instant messaging (IM) is seen as overly intrusive or informal for scheduling, while in others, email is preferred for documentation.
The Communications Management Plan: This plan specifically documents " person or groups who will receive the information " and " methods or technologies used to convey the information. " By asking for preferences, the Business Analyst (BA) can tailor the approach for each stakeholder, significantly increasing the response rate.
Engagement: Directly asking stakeholders how they want to be reached demonstrates respect for their time and local norms, which is a key component of Manage Stakeholder Engagement.
Analysis of other options:
B (Confirm time zone and work days): While important for scheduling the content of the meeting, knowing the time zone does not fix the issue of a stakeholder ignoring a specific channel (like IM). This is a logistical detail, whereas Choice A addresses the behavioral/preferred method of contact.
C (Check with the IT department): While technical issues can occur, in a global project environment, " no response " is more likely a communication style or engagement issue than a total system failure. This should only be done if a communication method was previously working and suddenly stopped.
D (Assume the meeting is accepted): This is a high-risk and unprofessional approach. It violates the " closed- loop " communication principle (Feedback) and often leads to empty meetings and project delays when the SME inevitably does not show up.
Key Concept: The Project Management Institute (PMI) emphasizes that the sender is responsible for ensuring the message is clear and received. By proactively identifying the preferred communication method (Choice A), the project team reduces " noise " and ensures that global stakeholders remain engaged and informed, regardless of their location.