正解:B
According to the PMBOK Guide under the Develop Schedule process, a Project Network Diagram is a graphical representation of the logical relationships (dependencies) among the project schedule activities.
* Path Identification: A " path " is defined as any continuous sequence of activities from the Start node to the Finish node.
* Analysis of the Network Structure: In the standard PMI practice question regarding nodes A through I (as referenced in your previous question, No. 259), the network branches at two specific decision points:
* First Branch: From Node A, the path can go to either B or D.
* Convergence: Both paths (B-C and D-E) converge at Node F.
* Second Branch: From Node F, the path can go to either G or H.
* Final Convergence: Both G and H lead to the final Node I.
Calculation of Total Paths: To find the total number of possible paths, we identify all unique routes from start to finish:
* Path 1: A - > B - > C - > F - > G - > I
* Path 2: A - > B - > C - > F - > H - > I
* Path 3: A - > D - > E - > F - > G - > I
* Path 4: A - > D - > E - > F - > H - > I
Comparison with other options:
* A. 3: This would miss one of the combinations of the two branching points.
* C and D. 6 or 7: These numbers would imply additional cross-dependencies or loops that are not present in a standard Precedence Diagramming Method (PDM) used for these specific PMI examination questions.