プロジェクトマネージャーは、プロジェクトのスコープをより小さな部分に分割し、これ以上の細分割が必要なくなるまでこのプロセスを繰り返します。この時点で、プロジェクトマネージャは各要素のコストとアクティビティを見積もることができます。
これらの要素は何と呼ばれていますか?
正解:B
According to the PMBOK Guide, the process described is Decomposition, which is the primary technique used in the Create WBS (Work Breakdown Structure) process.
* Definition of a Work Package: A work package is the lowest level of the Work Breakdown Structure. It is the point at which the cost and duration for the work can be reliably estimated and managed.
* The Goal of Decomposition: The project manager subdivides project deliverables into smaller, more manageable components. This process continues until the work is defined at a level of detail that allows for:
* Cost Estimation: Assigning a specific budget to the work.
* Activity Definition: Breaking the work package further into schedule activities.
* Monitoring and Control: Tracking progress against a specific baseline.
* The 8/80 Rule: A common heuristic in project management is that a work package should be between 8 and 80 hours of effort. If it is larger, it may need further decomposition; if it is smaller, it might be too granular for the WBS level.
Analysis of Other Options:
* A. Project activities: These are even smaller than work packages. Activities are the specific actions required to produce a work package. They are defined during the Define Activities process (part of Schedule Management), not during the creation of the WBS (Scope Management).
* C. Planning packages: These are components of the WBS that are below the control account but above the work package level. They have known work content but lack detailed schedule activities. They are used for " Rolling Wave Planning " when details for a specific part of the project are not yet available.
* D. Project deliverables: While work packages are deliverables, " deliverables " is a broad term that applies to any unique and verifiable product, result, or capability. The specific " elements " at the lowest level of the WBS resulting from decomposition are strictly defined as work packages.