主要な関係者はこれまでほとんど沈黙を守ってきた。リソースを最適化するため、関係者はチームメンバーの一人を別のプロジェクトに異動させたいと考えているが、プロジェクトマネージャーは同意していない。
プロジェクトマネージャーは何をすべきでしょうか?
正解:D
The correct answer is D because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response - D. Track the actual usage of resources and compare with estimated usage. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision- quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK Guide Eighth Edition topics: people, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.