チームメンバーが承認されずにプロジェクト会議を欠席した場合、基本規則に定義されているようにペナルティが科せられます。このチームメンバーおよび他のチームメンバーは、プロジェクトに関してこのルールを見るのは初めてであり、ペナルティには同意しないと主張しています。
この状況を避けるためにプロジェクトマネージャーは何をすべきでしたか?
正解:A
The project charter is a document that authorizes the project and defines its objectives, scope, stakeholders, and high-level risks. It also includes the project management approach and the roles and responsibilities of the project team. The project charter should be distributed to all team members and other key stakeholders to ensure their awareness and alignment with the project vision and expectations. The project charter also contains the project ground rules, which are the agreed-upon norms and behaviors that guide the team's interactions and collaboration. The ground rules should be clear, specific, measurable, and enforceable. They should also be reviewed and updated periodically to reflect any changes in the project environment or team dynamics. By distributing the project charter to all team members, the project manager can avoid misunderstandings, conflicts, and disagreements regarding the project ground rules and the consequences of violating them. References: PMBOK Guide, 6th edition, section 4.1.3.1; PMP Exam Prep, 10th edition, page
93